Donohue bridge -- a vital overpass between the industrial sector and downtown Sarnia posed a unique challenge due to the unforeseen circumstances and appraisal that led to an increase of 250% in the requirements for workload and resources. The existing condition of the deck was in much worse shape and deterioration than anticipated in tender drawings. Although the rehabilitation quantity increased drastically, the LCI team was able to fully complete and deliver on the project by its targeted timeline, finishing the project by the end of November 2018.

Location Sarnia, ON
Value $5.9M
Client City of Sarnia
Consultant Wood Engineering

Key Skills Applied

Rehabilitation of Deck Surface

Rehabilitation of Parapet Wall & Barrier Wall

Substructure Repairs, Including Bearing Pad Replacement